Who Actually Pays for the AI Data Center Boom?

Updated: 6 hours ago
Part 1 of 3 in the series Who Pays for the AI Grid.
Who actually pays for the AI data center boom? Probably not who you think.
PJM's capacity market just hit a wall. FERC only partly approved a 6.8 GW backstop procurement capped at $555/MW-day, and the auction is now delayed indefinitely. One Virginia co-op alone faced roughly $2B in potential collateral.
Here's the twist. Capacity costs are spread across the whole PJM footprint. The tax base stays local.
Host states collect property and equipment tax revenue and are moving to large-load tariffs that make data centers carry more of their own cost.
Ratepayers in states with few data centers pay higher regional capacity prices and get none of the offset.
Strategic finance takeaways
Power is moving from an opex line to a balance sheet line for developers
Collateral carry and interconnection deposits belong in every pro forma
Smaller developers without investment grade tenants feel it next
Bottom line: In PJM, the AI buildout quietly moves money from states that don't host data centers to states that do.
Who should carry the cost of new large loads: the grid, the ratepayer, or the developer?
Background: Utility Dive